The Tenant Delays described above shall only be deemed a Tenant Delay if Landlord has first given Tenant notice (which notice may be verbal, written or given electronically by email) that a situation exists which constitutes a Tenant Delay, provided that, if notice has been given pursuant to another section of this Lease for such event or failure no further notice shall be required hereunder.

 

(2)                                 Tenant Obligations with Respect to Tenant Delays.

 

(a)                                 Tenant covenants that no Tenant Delay shall delay commencement of the Term or the obligation to pay Annual Fixed Rent or Additional Rent, regardless of the reason for such Tenant Delay or whether or not it is within the control of Tenant or any such employee. Landlord’s Work shall be deemed substantially completed as of the date when Landlord’s Work would have been substantially completed but for any Tenant Delays, as determined by Landlord in the exercise of its good faith business judgment.

 

(b)                                 Tenant shall reimburse Landlord the amount, if any, by which the cost of Landlord’s Work is actually increased as the result of any Tenant Delay.

 

(c)                                  Any amounts due from Tenant to Landlord under this Section 1.1(C)(2) shall be due and payable within thirty (30) days of billing therefore (except that amounts due in connection with Change Orders shall be paid as provided in Section 1.5), and shall be considered to be Additional Rent. Nothing contained in this Section 1.1(C)(2) shall limit or qualify or prejudice any other covenants, agreements, terms, provisions and conditions contained in the Lease.

 

1.2                               Outside Completion Date

 

If Landlord shall have failed substantially to complete Landlord’s Work in the Premises described in the Plans on or before the Outside Completion Date as defined in Section 1.1 of the Lease (which date shall be extended automatically for such periods of time as Landlord is prevented from proceeding with or completing the same by reason of Landlord’s Force Majeure as defined in Section 6.1 of the Lease or any Tenant Delay, Tenant shall have the right to terminate the Lease by giving notice to Landlord of Tenant’s desire to do so before such completion and within the time period from the Outside Completion Date (as so extended) until the date which is thirty (30) days subsequent to the Outside Completion Date (as so extended); and, upon the giving of such notice, the term of the Lease shall cease and come to an end without further liability or obligation on the part of either party (and if Tenant is then in occupancy, Tenant shall yield up the Premises as required by this Lease at the expiration or earlier termination of the Term) unless, within thirty (30) days after receipt of such notice, Landlord substantially completes Landlord’s Work; and such right of termination shall be Tenant’s

 